This article is aimed at spreadsheet literate people who are involved in planning and scheduling production
activities. The techniques and formulas are being used by manufacturing companies daily; this is
a practical, not an academic, exercise.
Background
I have designed, built and implemented production scheduling systems for manufacturing
companies for over 11 years. When PC's and spreadsheets were less capable than they are now, we
used spreadsheets to design and prototype scheduling algorithms, and to train on some of the principles
of scheduling. Prototype designs were then handed over to software developers to write in more resilient
and efficient programming languages.
Impatient clients pressured us to throw several thousand records of data at the
prototypes and use them for live scheduling, before handing them to the software developers.
So, in order to 'shoehorn' a big scheduling task into a small PC, we recorded macros that wrote a
formula, copied it down, overwrote the cells with values, then moved on to the next column, so
that no memory consuming live formulas were left behind. Typically, most of the macro code prepared
downloaded data for scheduling, and generated reports from the schedule, with only a small portion
of the macro calculating the schedule itself. We ended up with big cumbersome macro driven scheduling
systems that locks out ordinary, spreadsheet literate people.
Thankfully we now have Pentium III's which will handle large amounts of data,
and have features such as Excel's PivotTable which will re-arrange and summarize data
for scheduling, and prepare reports without writing macros. It makes the job, of
building a scheduling system with a spreadsheet, a whole lot easier, and within the capability
of the average spreadsheet user.
The Case for Spreadsheets
There is a worldwide shortage of IT and
programming skills, but in most businesses a good depth of spreadsheet literacy
has developed. With some assistance, manufacturers can harness these skills,
uplift them, and end up with user- maintainable production scheduling systems.
The cost is considerably less than implementing one of the scheduling packages,
and the risk of being stranded without IT support, is lower. It must be
recognized, however that spreadsheets may be good for manipulating data, but
they are not transaction processors, and it is wise to interface to a host ERP
system.
Structured and Disciplined Approach
Spreadsheets have earned themselves a bad reputation
amongst software purists, because they can, and often are, used in an unstructured
way. Building a scheduling system requires a structured and disciplined
approach. Please resist the trap, that many fall into, of creating a table on a
single worksheet that looks like the report that you want to see. The approach
used here is to create lists in the form of databases, with a heading at the
top of each column, and with universal formulas that can be copied and pasted
down a column, and work on every row. If all the calculations are done in a
structured database, then reports, with sub-totals and charts, can easily be
created with a PivotTable.
Time Cascades Downwards
| Jobs |
Hours |
Start |
Stop |
| |
| Job A | 7 | 0 | 7 |
| Job B | 12 | 7 | 19 |
| Job C | 4 | 19 | 23 |
| Job D | 5 | 23 | 28 |
| Job E | 8 | 28 | 36 |
|
Here is a very simple finite schedule. It starts at hour zero, and the next job
starts when the previous one finishes.
Time cascades downwards in a pattern like this:
|
Re-sequencing the Schedule
| Seq |
Jobs |
Hours |
Start |
Stop |
Due |
On time |
| |
| 1 | Job A | 7 | 0 | 7 | 24 | TRUE |
| 2 | Job B | 12 | 7 | 19 | 24 | TRUE |
| 3 | Job C | 4 | 19 | 23 | 24 | TRUE |
| 4 | Job D | 5 | 23 | 28 | 24 | FALSE |
| 5 | Job E | 8 | 28 | 36 | 24 | FALSE |
|
Here is the same schedule with a job sequence and a due
date added. You can see that there is 36 hours of work, which is all due in 24
hours time - we have a problem. This is a good opportunity to illustrate the
essential difference between finite scheduling and capacity planning. Capacity
planning would tell you that you have a problem by saying you are 150% loaded.
Finite scheduling tells you about the problem by saying that out of 5 jobs, two
are going to be late. Lets see what it would look like if we left Job B till
last. We change sequence 2 to 6 and hit the sort icon.
|
| Seq |
Jobs |
Hours |
Start |
Stop |
Due |
On time |
| |
| 1 | Job A | 7 | 0 | 7 | 24 | TRUE |
| 3 | Job C | 4 | 7 | 11 | 24 | TRUE |
| 4 | Job D | 5 | 11 | 16 | 24 | TRUE |
| 5 | Job E | 8 | 16 | 24 | 24 | TRUE |
| 6 | Job B | 12 | 24 | 36 | 24 | FALSE |
|
Now only one job is going to be late. I would argue that
finite scheduling gives you better management information than capacity
planning does. In this simplistic example it is all very obvious, but if you
had 500 jobs to do in the next 6 weeks, you would need a tool to do the
calculations for you.
|
A Simple Gantt Chart
The mistake that many people make when constructing a
spreadsheet based schedule, is to start by making a Gantt chart with time
running from left to right. The technique here is to recognize that a Gantt
chart is merely a report that represents time in buckets, whereas the
calculations run downwards and are bucketless.
| Size of bucket: |
1 |
Hr |
|
| |
| Jobs | Hours | Start | Stop |
1 | 2 | 3 | 4 | 5 |
6 | 7 | 8 | 9 | 10 | 11 |
12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 |
20 | 21 | 22 | 23 | 24 | 25 | 26 |
| |
| Job A | 7 | 0 | 7 |
1 | 1 | 1 | 1 |
1 | 1 | 1 |
| | | | | |
| | | | | |
| | | | | |
|
| Job C | 4 | 7 | 11 |
| | | | |
| |
1 | 1 | 1 | 1 |
| | | | | |
| | | | | |
| | |
| Job D | 5 | 11 | 16 |
| | | | | |
| | | | |
1 | 1 | 1 | 1 |
1 |
| | | | | |
| | | |
| Job E | 8 | 16 | 24 |
| | | | | |
| | | | | |
| | | | 1 |
1 | 1 | 1 |
1 | 1 | 1 | 1 |
| |
| Job B | 12 | 24 | 36 |
| | | | | |
| | | | | |
| | | | | |
| | | | | |
1 | 1 |
The formula in each cell of the Gantt chart looks up at
the top row, and flags the cell if it lies between the stop and start of the
job, and conditional formatting is used to color it. The size of the bucket is variable, for example:
| Size of bucket: |
2 |
hrs |
|
| |
| Jobs | Hours | Start | Stop |
2 | 4 | 6 | 8 |
10 | 12 | 14 | 16 | 18 | 20 | 22 |
24 | 26 | 28 | 30 | 32 | 34 | 36 | 38 |
40 | 42 |
| |
| Job A | 7 | 0 | 7 |
1 | 1 | 1 |
| | | | | |
| | | | | |
| | | | | |
| Job C | 4 | 7 | 11 |
| | |
1 | 1 |
| | | | | |
| | | | | |
| | | |
| Job D | 5 | 11 | 16 |
| | | | |
1 | 1 | 1 |
| | | | | |
| | | | | |
|
| Job E | 8 | 16 | 24 |
| | | | | |
| |
1 | 1 | 1 | 1 |
| | | | | |
| | |
| Job B | 12 | 24 | 36 |
| | | | | |
| | | | | |
1 | 1 | 1 | 1 |
1 | 1 |
| | |
Change-over Matrix
Often change-over time can be saved by undertaking jobs in
a certain sequence. A typical example would be a paint line where a change from
a dark color to a light color requires a much longer cleaning process than
from a light color to a dark color. The differential change over times
are expressed in the matrix to the
left, and the schedule on the right has an extra column for change-overs (C/O).
| | Hours |
| |
| |
| |
| |
| |
| |
| To/From | Job A | Job B | Job C | Job D | Job E |
| Seq | Jobs | Hours | C/O | Start |
Stop | Due |
On Time |
| Job A | 0.0 | 0.5 | 1.0 | 1.5 | 2.0 |
| 1 | Job B | 11 | 0 | 0 |
11 | 24 | TRUE |
| Job B | 0.1 | 0.0 | 0.5 | 1.0 | 1.5 |
| 2 | Job E | 7 | 1.5 | 11 |
19.5 | 24 | TRUE |
| Job C | 0.2 | 0.1 | 0.0 | 0.5 | 1.0 |
| 3 | Job A | 6 | 0.4 | 19.5 |
25.9 | 24 | FALSE |
| Job D | 0.3 | 0.2 | 0.1 | 0.0 | 0.5 |
| 4 | Job D | 4 | 1.5 | 25.9 |
31.4 | 24 | FALSE |
| Job E | 0.4 | 0.3 | 0.2 | 0.1 | 0.0 |
| 5 | Job C | 3 | 0.1 | 31.4 |
34.5 | 24 | FALSE |
| |
| | Total Change-overs |
3.5 | Hrs | |
It is assumed that the first job has already been set up,
so has a change-over time of zero. Now re-sequencing the schedule becomes a
little more challenging. The above sequence would mean that 3 jobs would be
late and 3.5 hours would be spent on change-overs, so let us see if we can
sequence more intelligently:
| Seq | Jobs |
Hours | C/O |
Start | Stop |
Due | On time |
| 1 | Job E |
7 | 0 | 0 | 7 | 24 | TRUE |
| 2 | Job D |
4 | 0.1 | 7 | 11.1 | 24 | TRUE |
| 3 | Job C |
3 | 0.1 | 11.1 | 14.2 | 24 | TRUE |
| 4 | Job A |
6 | 0.2 | 14.2 | 20.4 | 24 | TRUE |
| 5 | Job B |
11 | 0.5 | 20.4 | 31.9 | 24 | TRUE |
| |
| Total Change-overs |
0.9 |
Hrs |
|
|
Again, we change the sequence numbers and click in the
sort icon. That's better, only one late job and 0.9 of an hour on change-overs.
By reading the change-over matrix the behavior of the schedule is much more
sensitive to sequence changes.
|
Base 1900 Date
NOW:36982.9016635417 Days since 1 January 1900 |
| Here are some different formats of the date: |
| |
| 21:38:24 | Sun |
| 09:38:24 PM | Sunday |
| 09:38 PM | Apr |
| 4/1 | April |
| 4/1/01 | 2001 |
| 1-Apr | 01-Apr-01 |
| April-01 | April 1, 2001 |
|
Up to now we have referred to points in
time as, for example, "36 hours into the schedule" from hour zero. Excel and
other spreadsheets use days, rather than hours as the primary measure of time,
and the starting point is midnight on 1st of January of the year
1900. All time calculations are done in days, but there are enough decimal
places of a day to measure less than a 3000th of a second. This
makes a spreadsheet particularly useful for date and time calculations, as we
only have to concern ourselves with one unit of measure, a day. A date or
elapsed time measured in days may be formatted and viewed as seconds, minutes,
hours, day of the week, day of the month, weeks, months or years.
|
If we express our schedule using base 1900 dates our
schedule would now look like this, and the starting point will no longer be
hour zero, so we have to establish a starting point for the schedule. In this
case midnight on 1 April this year.
| Start of Schedule: |
01 Apr 12:00 AM |
| |
| Jobs |
Hours |
Days |
Start | Stop |
| |
| Job A | 7 | 0.2917 | 01 Apr 12:00 AM | 01 Apr 07:00 AM |
| Job B | 12 | 0.5000 | 01 Apr 07:00 AM | 01 Apr 07:00 PM |
| Job C | 4 | 0.1667 | 01 Apr 07:00 PM | 01 Apr 11:00 PM |
| Job D | 5 | 0.2083 | 01 Apr 11:00 AM | 02 Apr 04:00 PM |
| Job E | 8 | 0.3333 | 02 Apr 04:00 AM | 02 Apr 12:00 PM |
|
Working With a Calendar
Our simple schedule assumes that we work 24 hours a day
for 7 days per week, which is fine if we are scheduling a continuous process
such as an oil refinery or a paper mill, but most manufacturers work to a shift
calendar. Here is an example of a shift calendar:
| Hrs |
Day |
Begin |
End |
Cum. Days |
|
| |
| 2 | Mon | 04 Jun 08:00 AM | 04 Jun 10:00 AM | 0.083 |   | Duration: | 22.8 | Hrs |
| 2.75 | Mon | 04 Jun 10:15 AM | 04 Jun 01:00 PM | 0.198 |   | Start: | 04 Jun 12:27 PM | Mon |
| 2 | Mon | 04 Jun 01:30 PM | 04 Jun 03:30 PM | 0.281 |   | |
| 2.25 | Mon | 04 Jun 03:45 PM | 04 Jun 06:00 PM | 0.375 |   | Start row: | 7 | Calc 1 |
| 3 | Mon | 04 Jun 07:00 PM | 04 Jun 10:00 PM | 0.500 |   | Cum. day: | 0.175 | Calc 2 |
| 2 | Tue | 05 Jun 08:00 AM | 05 Jun 10:00 AM | 0.583 |   | Stop row: | 17 | Calc 3 |
| 2.75 | Tue | 05 Jun 10:15 AM | 05 Jun 01:00 PM | 0.698 |   | Stop: | 06 Jun 11:15 AM | Wed |
| 2 | Tue | 05 Jun 01:30 PM | 05 Jun 03:30 PM | 0.781 |   | |
| 2.25 | Tue | 05 Jun 03:45 PM | 05 Jun 06:00 PM | 0.875 |   | |
| 3 | Tue | 05 Jun 07:00 PM | 05 Jun 10:00 PM | 1.000 |   | |
| 2 | Wed | 06 Jun 08:00 AM | 06 Jun 10:00 AM | 1.083 |   | |
| 2.75 | Wed | 06 Jun 10:15 AM | 06 Jun 01:00 PM | 1.198 |   | |
| 2 | Wed | 06 Jun 01:30 PM | 06 Jun 03:30 PM | 1.281 |   | |
| 2.25 | Wed | 06 Jun 03:45 PM | 06 Jun 06:00 PM | 1.375 |   | |
| 3 | Wed | 06 Jun 07:00 PM | 06 Jun 10:00 PM | 1.500 |   | |
Each row of the calendar is a working period, and the "Cum. Days" column tracks the cumulative
days from the beginning of the calendar. The calculations to the right of the calendar assume
that we start a job at 12:27pm on 4 June and work for 22.8 hours, when will the job stop?
There are a series of formulas that reference the calendar and calculate the stop time, and
the detailed derivation of the formulas is set out in the tutorial. Broadly the formulas work
in this way: The job starts during the working period on row 7, 0.175 days from the start of
the calendar, and the job will stop during row 17 of the calendar at 11:15am on 6 June.
This is an example of how the schedule looks when we work through the calendar:
| Start of Schedule |
20 JUN 10:30 AM |
  |
| |
| Jobs | Hours | Days | Start | Calc1 | Calc2 | Calc3 | Stop |
| Job A | 7 | 0.292 | 20 Jun 10:30 AM | 65 | 5.844 | 68 | 20 Jun 07:15 PM | |
| Job B | 12 | 0.500 | 20 Jun 07:15 PM | 68 | 6.135 | 73 | 21 Jun 07:15 PM |
| Job C | 4 | 0.167 | 21 Jun 07:15 PM | 73 | 6.635 | 74 | 22 Jun 09:15 AM |
| Job D | 5 | 0.208 | 22 Jun 09:15 AM | 74 | 6.802 | 76 | 22 Jun 03:00 PM |
| Job E | 8 | 0.333 | 22 Jun 03:00 PM | 76 | 7.01 | 80 | 25 Jun 02:00 PM |
Jobs That Pass Through Multiple Work Centers
So far the start of a job is determined by the stop of the
previous job, but where a job goes through several operations on different work
stations, a work station may have to wait for the job to emerge from the
previous work station before it can start. Here is an example of Jobs A, B and
C passing through work centers 6, 7 and 8:
| |
Start of Schedule: |
  |
4/6 02:00 |
|
| |
4/6 |
5/6 |
6/6 |
| W/C | Jobs |
Job/Op | Duration Hrs |
Prev. Op. | Stop of Prev. Op. |
Wait Hrs | Start |
Stop | 00:00 |
08:00 | 16:00 |
00:00 | 08:00 |
16:00 | 00:00 |
08:00 | 16:00 |
| 6 | Job A |
A/1 | 12 |
A/0 |   |
0 | 4/6 02:00 |
4/6 14:00 | 6 |
6 |   |
  |   |
  |   |
  |   |
| 6 | Job B | B/1 | 18 | B/0 |   | 0 | 4/6 14:00 | 5/6 08:00 |   | 2 | 8 | 8 |   |   |   |   |   |
| 6 | Job C | C/1 | 15 | C/0 |   | 0 | 5/6 08:00 | 5/6 23:00 |   |   |   |   | 8 | 7 |   |   |   |
| 7 | Job A | A/2 | 10 | A/1 | 4/6 14:00 | 12 | 4/6 14:00 | 5/6 00:00 |   | 2 | 8 |   |   |   |   |   |   |
| 7 | Job B | B/2 | 14 | B/1 | 5/6 08:00 | 8 | 5/6 08:00 | 5/6 22:00 |   |   |   |   | 8 | 6 |   |   |   |
| 7 | Job C | C/2 | 6 | C/1 | 5/6 23:00 | 1 | 5/6 23:00 | 6/6 05:00 |   |   |   |   |   | 1 | 5 |   |   |
| 8 | Job A | A/3 | 8 | A/2 | 5/6 00:00 | 22 | 5/6 00:00 | 5/6 08:00 |   |   |   | 8 |   |   |   |   |   |
| 8 | Job B | B/3 | 11 | B/2 | 5/6 22:00 | 14 | 5/6 22:00 | 6/6 09:00 |   |   |   |   |   | 2 | 8 | 1 |   |
| 8 | Job C | C/3 | 14 | C/2 | 6/6 05:00 | 0 | 6/6 09:00 | 6/6 23:00 |   |   |   |   |   |   |   | 7 | 7 |
Each operation looks up the stop time of the previous operation (if there is one), it also
looks at the stop of the previous job on the work center, and uses the later of the two to
establish the start time. Note the gaps where a work center has to wait.
A similar technique is used when two or
more manufactured components meet at an assembly operation. A separate column
is set up for each component, and the stop dates determine the start of the
assembly operation.
Notice also that the Gantt chart
buckets are 8 hour periods labeled with a base 1900 date and time, and that
instead of simple flags, the buckets show the number of job hours in each
bucket. The Gantt chart formula is more
involved than a simple flag, and a full explanation is in the tutorial.
Now is a good point to introduce some
Theory of Constraints (TOC) thinking. Have a look at Job C going through work
center 7. It starts at 11:00pm as soon as it comes off work center 6, runs till
5:00am, then waits for 4 hours for work center 8 to become available. Why start
it earlier than you have to, and have it lying in WIP?
Push-Pull-Push 3 Pass Logic
In Eli Goldratt's book, The Haystack Syndrome, he describes a scheduling technique which he
likens to "leveling the ruins" with a bulldozer in 3 passes, forwards, backwards, and forwards
again. A very similar 3 pass algorithm can be done with a spreadsheet. The details of the
calculations are set out in the tutorial, but in essence this is how it works. There are two
jobs on the same work center, one due in 24 hours time and the other in 48 hours:
| |  | |
| | Day 1 | Day 2 | |
| Jobs | Hours | Due | 0 | 8 | 16 | 24 | 32 | 40 | 48 | 56 |
| |
PUSH  |
| |
| Job A | 32 | 24 | | | | | | | | |
| Job B | 8 | 48 | | | | | | | | |
| |
PULL  |
| |
| Job A | 32 | 24 | | | | | | | | |
| Job B | 8 | 48 | | | | | | | | |
| |
PUSH AGAIN  |
| |
| Job A | 32 | 24 | | | | | | | | |
| Job B | 8 | 48 | | | | | | | | |
|
The first pass starts now and does both jobs as soon as possible
The second pass starts each job just in time to meet the due date. Job A will have to have
started yesterday. Obviously, this is not possible.
The third pass pushes Job A to a feasible start time, and leaves Job B where it was, to
leave a schedule which is the best due date performance that can be achieved, but with a "pull"
approach.
When the algorithm is applied to a multiple work center schedule, it has the effect of
delaying an operation until the next operation is ready for it, discouraging the building of WIP
for the sake of keeping machines busy. The second pass works backwards, with the calculations
going up the columns instead of down, and each operation may be influenced by the start of the
next operation.
|
Repetitive Production and Transfer Batches
Up to now our examples have been of jobs with a duration in hours. Here is an example of
repetitive production, each job being for batches of multiple products that run through each
work center at a rate per hour. First let us assume that the entire batch must be complete at
a work center before it can go to the next work center.
| Start of Schedule: | | 14/3 04:00 | |
| Transfer batch: | | | |
| |
| | 14/3 | 15/3 | 16/3 | 17/3 |
| Work Center | Product | Qty | Units/Hr | Wait Hrs |
00:00 | 08:00 | 16:00 | 00:00 | 08:00 | 16:00 | 00:00 | 08:00 | 16:00 | 00:00 | 08:00 | 16:00 |
| 6 | Prod A | 180 | 13 | 0.0 | 52 | 104 | 24 | | | | | | | | | |
| 6 | Prod B | 300 | 12 | 0.0 | | | 74 | 96 | 96 | 34 | | | | | | |
| 6 | Prod C | 220 | 15 | 0.0 | | | | | | 77 | 120 | 23 | | | | |
| 7 | Prod A | 180 | 21 | 13.8 | | | 129 | 51 | | | | | | | | |
| 7 | Prod B | 300 | 19 | 16.4 | | | | | | 98 | 152 | 50 | | | | |
| 7 | Prod C | 220 | 22 | 0.0 | | | | | | | | 118 | 102 | | | |
| 8 | Prod A | 180 | 16 | 22.4 | | | | 89 | 91 | | | | | | | |
| 8 | Prod B | 300 | 17 | 21.0 | | | | | | | | 91 | 136 | 73 | | |
| 8 | Prod C | 220 | 18 | 0.0 | | | | | | | | | | 67 | 144 | 9 |
Now see the impact of transferring products between work centers in batches of 10. What took
4 days, now takes less than 3 days:
| Start of Schedule: | 14/3 04:00 | |
| Transfer batch: | | |
| |
| | 14/3 | 15/3 | 16/3 | 17/3 |
| Work Center | Product | Qty | Units/Hour | Wait Hrs |
00:00 | 08:00 | 16:00 | 00:00 | 08:00 | 16:00 | 00:00 | 08:00 | 16:00 | 00:00 | 08:00 | 16:00 |
| 6 | Prod A | 180 | 13 | 0.0 | 52 | 104 | 24 | | | | | | | | | |
| 6 | Prod B | 300 | 12 | 0.0 | | | 74 | 96 | 96 | 34 | | | | | | |
| 6 | Prod C | 220 | 15 | 0.0 | | | | | | 77 | 120 | 23 | | | | |
| 7 | Prod A | 180 | 21 | 0.5 | 46 | 104 | 30 | | | | | | | | | |
| 7 | Prod B | 300 | 19 | 0.1 | | | 68 | 96 | 96 | 40 | | | | | | |
| 7 | Prod C | 220 | 22 | 0.0 | | | | | | 70 | 121 | 30 | | | | |
| 8 | Prod A | 180 | 16 | 1.1 | 38 | 104 | 38 | | | | | | | | | |
| 8 | Prod B | 300 | 17 | 0.0 | | | 60 | 96 | 96 | 48 | | | | | | |
| 8 | Prod C | 220 | 18 | 0.0 | | | | | | 61 | 121 | 38 | | | | |
If a fast operation follows a slow operation, as in this
example, it will stop and start as it waits for each transfer batch to reach
it. The 3 pass algorithm avoids this by delaying the start of the fast
operation so that it catches up with the slow operation by the time the job
finishes. To ensure that the second operation does not finish before the first,
it needs to look up the stop, as well as the start of the previous operation.
For simplicity these detailed calculations are hidden in this example, but they
are explained in the tutorial.
Notice that the Gantt chart now shows the number of units
produced in each time bucket. This is done by taking the hours per bucket, as
in the previous Gantt chart, and multiplying by a rate per hour.
Sequencing a Multiple Work Center Schedule
These simple examples show each product with the same
routing, work center 6 then 7 then 8. Some processes work this way, so
sequencing may simply be a matter or sorting operations by due date within work
center. Manufacturing processes where the products follow very different
routings, may require more sophisticated sequencing rules to be calculated. One
such calculation works as follows:
- the loading on each work center, in hours, is calculated
- for each job the most heavily loaded work center that it passes through, is
identified
- we consider this to be the job's constraint
- assuming infinite capacity (for now) we calculate the latest time that the job must
start on the constraint, in order to meet its due date
- we then sort by this date to determine the sequence through each work center
Often it is a good idea to allow the sequences to be overridden manually to see how
the schedule responds to changes in sequence.
Putting it All Together
In
my experience of several hundred scheduling systems, each one is different, but
a typical spreadsheet scheduling system may have the following features:
- ODBC interfaces with a host ERP or MRP system
- routings through multiple work centers
- a BOM with several manufactured components at an assembly operation
- a separate calendar for each work center
- a change-over matrix for each work center
- repetitive production
- different transfer batch sizes for each product between each work center
- demand that may explode into several thousand operations
- a rough pre-schedule to establish a sequence for each operation
- the push-pull-push 3 pass algorithm
- Gantt charts with variable sized time buckets
The flow of data through the system would typically be as follows:
Such a system would:
- have about 20 pages in a workbook
- be up to 30Mb in size
- have finite scheduling calculations with up to 150 columns
and several thousand rows
- contain about 10 PivotTables
- have NO macro code
- take from 5 to 30 seconds to re-schedule
Author:
Tony Rice
production-scheduling.com
24 Kenilworth Drive,
Kloof 3610, KwaZulu/Natal,
South Africa
|
Tony Rice graduated with a BA honors Business Degree from Manchester. He worked as a management accountant for
the electronics companies, Pye/Philips and Sinclair in the UK. In 1981 he came to South Africa to join Deloitte and
Touche Consulting, and later moved to KPMG Consulting as a Director.
Since 1990 Mr. Rice has operated as an independent consultant specializing in production scheduling
and supply chain integration.