- Tony Rice, production-scheduling.com, South Africa

Introduction

For years spreadsheets have been used to design and prototype scheduling systems. They have now grown up, and are being used to develop serious production scheduling applications. A comprehensive tutorial available at no charge at www.production-scheduling.com and this paper summarizes it, introduces some of the concepts, and illustrates what is possible with a spreadsheet.


Email this article to colleagues and friends Send this article to colleagues and friends
Send us you comments about this article Send us your comments
Download this article in PDF Format  Download this article in PDF Format
 

 

This article is aimed at spreadsheet literate people who are involved in planning and scheduling production activities. The techniques and formulas are being used by manufacturing companies daily; this is a practical, not an academic, exercise.

Background

I have designed, built and implemented production scheduling systems for manufacturing companies for over 11 years. When PC's and spreadsheets were less capable than they are now, we used spreadsheets to design and prototype scheduling algorithms, and to train on some of the principles of scheduling. Prototype designs were then handed over to software developers to write in more resilient and efficient programming languages.

Impatient clients pressured us to throw several thousand records of data at the prototypes and use them for live scheduling, before handing them to the software developers. So, in order to 'shoehorn' a big scheduling task into a small PC, we recorded macros that wrote a formula, copied it down, overwrote the cells with values, then moved on to the next column, so that no memory consuming live formulas were left behind. Typically, most of the macro code prepared downloaded data for scheduling, and generated reports from the schedule, with only a small portion of the macro calculating the schedule itself. We ended up with big cumbersome macro driven scheduling systems that locks out ordinary, spreadsheet literate people.

Thankfully we now have Pentium III's which will handle large amounts of data, and have features such as Excel's PivotTable which will re-arrange and summarize data for scheduling, and prepare reports without writing macros. It makes the job, of building a scheduling system with a spreadsheet, a whole lot easier, and within the capability of the average spreadsheet user.

The Case for Spreadsheets

There is a worldwide shortage of IT and programming skills, but in most businesses a good depth of spreadsheet literacy has developed. With some assistance, manufacturers can harness these skills, uplift them, and end up with user- maintainable production scheduling systems. The cost is considerably less than implementing one of the scheduling packages, and the risk of being stranded without IT support, is lower. It must be recognized, however that spreadsheets may be good for manipulating data, but they are not transaction processors, and it is wise to interface to a host ERP system.

Structured and Disciplined Approach

Spreadsheets have earned themselves a bad reputation amongst software purists, because they can, and often are, used in an unstructured way. Building a scheduling system requires a structured and disciplined approach. Please resist the trap, that many fall into, of creating a table on a single worksheet that looks like the report that you want to see. The approach used here is to create lists in the form of databases, with a heading at the top of each column, and with universal formulas that can be copied and pasted down a column, and work on every row. If all the calculations are done in a structured database, then reports, with sub-totals and charts, can easily be created with a PivotTable.

Time Cascades Downwards

Jobs Hours Start Stop
 
Job A707
Job B12719
Job C41923
Job D52328
Job E82836
Here is a very simple finite schedule. It starts at hour zero, and the next job starts when the previous one finishes.

Time cascades downwards in a pattern like this:

Re-sequencing the Schedule

Seq Jobs Hours Start Stop Due On time
 
1Job A70724TRUE
2Job B1271924TRUE
3Job C4192324TRUE
4Job D5232824FALSE
5Job E8283624FALSE

Here is the same schedule with a job sequence and a due date added. You can see that there is 36 hours of work, which is all due in 24 hours time - we have a problem. This is a good opportunity to illustrate the essential difference between finite scheduling and capacity planning. Capacity planning would tell you that you have a problem by saying you are 150% loaded. Finite scheduling tells you about the problem by saying that out of 5 jobs, two are going to be late. Lets see what it would look like if we left Job B till last. We change sequence 2 to 6 and hit the sort icon.

Seq Jobs Hours Start Stop Due On time
 
1Job A70724TRUE
3Job C471124TRUE
4Job D5111624TRUE
5Job E8162424TRUE
6Job B12243624FALSE

Now only one job is going to be late. I would argue that finite scheduling gives you better management information than capacity planning does. In this simplistic example it is all very obvious, but if you had 500 jobs to do in the next 6 weeks, you would need a tool to do the calculations for you.

A Simple Gantt Chart

The mistake that many people make when constructing a spreadsheet based schedule, is to start by making a Gantt chart with time running from left to right. The technique here is to recognize that a Gantt chart is merely a report that represents time in buckets, whereas the calculations run downwards and are bucketless.

Size of bucket: 1 Hr  
 
JobsHoursStartStop  1 2 3 4 5  6 7 8 91011 1213141516171819 20212223242526
 
Job A707 1111 111                       
Job C4711          1111                  
Job D51116              1111 1            
Job E81624                   1 111 1111   
Job B122436                             11

The formula in each cell of the Gantt chart looks up at the top row, and flags the cell if it lies between the stop and start of the job, and conditional formatting is used to color it. The size of the bucket is variable, for example:

Size of bucket: 2 hrs  
 
JobsHoursStartStop  2 4 6 8 10121416182022 2426283032343638 4042
 
Job A707 111                     
Job C4711     11                   
Job D51116       111                
Job E81624           1111           
Job B122436               1111 11    

Change-over Matrix

Often change-over time can be saved by undertaking jobs in a certain sequence. A typical example would be a paint line where a change from a dark color to a light color requires a much longer cleaning process than from a light color to a dark color. The differential change over times are expressed in the matrix to the left, and the schedule on the right has an extra column for change-overs (C/O).

 Hours                  
To/FromJob AJob BJob CJob DJob E  SeqJobsHoursC/OStart StopDue On Time
Job A0.00.51.01.52.0  1Job B1100 1124TRUE
Job B0.10.00.51.01.5  2Job E71.511 19.524TRUE
Job C0.20.10.00.51.0  3Job A60.419.5 25.924FALSE
Job D0.30.20.10.00.5  4Job D41.525.9 31.424FALSE
Job E0.40.30.20.10.0  5Job C30.131.4 34.524FALSE
 
 Total Change-overs 3.5Hrs 

It is assumed that the first job has already been set up, so has a change-over time of zero. Now re-sequencing the schedule becomes a little more challenging. The above sequence would mean that 3 jobs would be late and 3.5 hours would be spent on change-overs, so let us see if we can sequence more intelligently:

SeqJobs HoursC/O StartStop DueOn time
1Job E 700724TRUE
2Job D 40.1711.124TRUE
3Job C 30.111.114.224TRUE
4Job A 60.214.220.424TRUE
5Job B 110.520.431.924TRUE
 
Total Change-overs 0.9 Hrs  

Again, we change the sequence numbers and click in the sort icon. That's better, only one late job and 0.9 of an hour on change-overs. By reading the change-over matrix the behavior of the schedule is much more sensitive to sequence changes.

Base 1900 Date

NOW:36982.9016635417
Days since 1 January 1900
Here are some different formats of the date:
 
21:38:24Sun
09:38:24 PMSunday
09:38 PMApr
4/1April
4/1/012001
1-Apr01-Apr-01
April-01April 1, 2001

Up to now we have referred to points in time as, for example, "36 hours into the schedule" from hour zero. Excel and other spreadsheets use days, rather than hours as the primary measure of time, and the starting point is midnight on 1st of January of the year 1900. All time calculations are done in days, but there are enough decimal places of a day to measure less than a 3000th of a second. This makes a spreadsheet particularly useful for date and time calculations, as we only have to concern ourselves with one unit of measure, a day. A date or elapsed time measured in days may be formatted and viewed as seconds, minutes, hours, day of the week, day of the month, weeks, months or years.

 

If we express our schedule using base 1900 dates our schedule would now look like this, and the starting point will no longer be hour zero, so we have to establish a starting point for the schedule. In this case midnight on 1 April this year.
Start of Schedule: 01 Apr 12:00 AM
 
Jobs Hours Days StartStop
 
Job A70.291701 Apr 12:00 AM01 Apr 07:00 AM
Job B120.500001 Apr 07:00 AM01 Apr 07:00 PM
Job C40.166701 Apr 07:00 PM01 Apr 11:00 PM
Job D50.208301 Apr 11:00 AM02 Apr 04:00 PM
Job E80.333302 Apr 04:00 AM02 Apr 12:00 PM

Working With a Calendar

Our simple schedule assumes that we work 24 hours a day for 7 days per week, which is fine if we are scheduling a continuous process such as an oil refinery or a paper mill, but most manufacturers work to a shift calendar. Here is an example of a shift calendar:

Hrs Day Begin End Cum. Days  
 
2Mon04 Jun 08:00 AM04 Jun 10:00 AM0.083 Duration:22.8Hrs
2.75Mon04 Jun 10:15 AM04 Jun 01:00 PM0.198 Start:04 Jun 12:27 PM Mon
2Mon04 Jun 01:30 PM04 Jun 03:30 PM0.281  
2.25Mon04 Jun 03:45 PM04 Jun 06:00 PM0.375 Start row:7Calc 1
3Mon04 Jun 07:00 PM04 Jun 10:00 PM0.500 Cum. day:0.175Calc 2
2Tue05 Jun 08:00 AM05 Jun 10:00 AM0.583 Stop row:17Calc 3
2.75Tue05 Jun 10:15 AM05 Jun 01:00 PM0.698 Stop:06 Jun 11:15 AMWed
2 Tue05 Jun 01:30 PM05 Jun 03:30 PM0.781  
2.25Tue05 Jun 03:45 PM05 Jun 06:00 PM0.875  
3Tue05 Jun 07:00 PM05 Jun 10:00 PM1.000  
2Wed06 Jun 08:00 AM06 Jun 10:00 AM1.083  
2.75Wed06 Jun 10:15 AM06 Jun 01:00 PM1.198  
2Wed06 Jun 01:30 PM06 Jun 03:30 PM1.281  
2.25 Wed06 Jun 03:45 PM06 Jun 06:00 PM1.375  
3Wed06 Jun 07:00 PM06 Jun 10:00 PM1.500  

Each row of the calendar is a working period, and the "Cum. Days" column tracks the cumulative days from the beginning of the calendar. The calculations to the right of the calendar assume that we start a job at 12:27pm on 4 June and work for 22.8 hours, when will the job stop? There are a series of formulas that reference the calendar and calculate the stop time, and the detailed derivation of the formulas is set out in the tutorial. Broadly the formulas work in this way: The job starts during the working period on row 7, 0.175 days from the start of the calendar, and the job will stop during row 17 of the calendar at 11:15am on 6 June.

This is an example of how the schedule looks when we work through the calendar:

Start of Schedule 20 JUN 10:30 AM  
 
JobsHoursDaysStartCalc1Calc2Calc3Stop
Job A70.29220 Jun 10:30 AM655.8446820 Jun 07:15 PM
Job B120.50020 Jun 07:15 PM686.1357321 Jun 07:15 PM
Job C40.16721 Jun 07:15 PM736.6357422 Jun 09:15 AM
Job D50.20822 Jun 09:15 AM746.8027622 Jun 03:00 PM
Job E80.33322 Jun 03:00 PM767.018025 Jun 02:00 PM

Jobs That Pass Through Multiple Work Centers

So far the start of a job is determined by the stop of the previous job, but where a job goes through several operations on different work stations, a work station may have to wait for the job to emerge from the previous work station before it can start. Here is an example of Jobs A, B and C passing through work centers 6, 7 and 8:

  Start of Schedule:   4/6 02:00  
  4/6 5/6 6/6
W/C Jobs Job/Op Duration Hrs Prev. Op. Stop of Prev. Op. Wait Hrs Start Stop 00:00 08:00 16:00 00:00 08:00 16:00 00:00 08:00 16:00
6 Job A A/1 12 A/0   0 4/6 02:00 4/6 14:00 6 6              
6Job BB/118B/0 04/6 14:005/6 08:00 288     
6Job CC/115C/0 05/6 08:005/6 23:00    87   
7Job AA/210A/14/6 14:00124/6 14:005/6 00:00 28      
7Job BB/214B/15/6 08:0085/6 08:005/6 22:00    86   
7Job CC/26C/15/6 23:0015/6 23:006/6 05:00     15  
8Job AA/38A/25/6 00:00225/6 00:005/6 08:00   8     
8Job BB/311B/25/6 22:00145/6 22:006/6 09:00     281 
8Job CC/314C/26/6 05:0006/6 09:006/6 23:00       77

Each operation looks up the stop time of the previous operation (if there is one), it also looks at the stop of the previous job on the work center, and uses the later of the two to establish the start time. Note the gaps where a work center has to wait.

A similar technique is used when two or more manufactured components meet at an assembly operation. A separate column is set up for each component, and the stop dates determine the start of the assembly operation.

Notice also that the Gantt chart buckets are 8 hour periods labeled with a base 1900 date and time, and that instead of simple flags, the buckets show the number of job hours in each bucket. The Gantt chart formula is more involved than a simple flag, and a full explanation is in the tutorial.

Now is a good point to introduce some Theory of Constraints (TOC) thinking. Have a look at Job C going through work center 7. It starts at 11:00pm as soon as it comes off work center 6, runs till 5:00am, then waits for 4 hours for work center 8 to become available. Why start it earlier than you have to, and have it lying in WIP?

Push-Pull-Push 3 Pass Logic

In Eli Goldratt's book, The Haystack Syndrome, he describes a scheduling technique which he likens to "leveling the ruins" with a bulldozer in 3 passes, forwards, backwards, and forwards again. A very similar 3 pass algorithm can be done with a spreadsheet. The details of the calculations are set out in the tutorial, but in essence this is how it works. There are two jobs on the same work center, one due in 24 hours time and the other in 48 hours:

  
 Day 1Day 2 
JobsHoursDue162432404856
 
PUSH   
 
Job A3224        
Job B848        
 
PULL   
 
Job A3224        
Job B848        
 
PUSH AGAIN   
 
Job A3224        
Job B848        

The first pass starts now and does both jobs as soon as possible

The second pass starts each job just in time to meet the due date. Job A will have to have started yesterday. Obviously, this is not possible.

The third pass pushes Job A to a feasible start time, and leaves Job B where it was, to leave a schedule which is the best due date performance that can be achieved, but with a "pull" approach.

When the algorithm is applied to a multiple work center schedule, it has the effect of delaying an operation until the next operation is ready for it, discouraging the building of WIP for the sake of keeping machines busy. The second pass works backwards, with the calculations going up the columns instead of down, and each operation may be influenced by the start of the next operation.

Repetitive Production and Transfer Batches

Up to now our examples have been of jobs with a duration in hours. Here is an example of repetitive production, each job being for batches of multiple products that run through each work center at a rate per hour. First let us assume that the entire batch must be complete at a work center before it can go to the next work center.

Start of Schedule: 14/3 04:00 
Transfer batch:   
 
 14/315/316/317/3
Work CenterProductQtyUnits/HrWait Hrs 00:0008:0016:0000:0008:0016:0000:0008:0016:0000:0008:0016:00
6Prod A180130.05210424         
6Prod B300120.0  74969634      
6Prod C220150.0     7712023    
7Prod A1802113.8  12951        
7Prod B3001916.4     9815250    
7Prod C220220.0       118102   
8Prod A1801622.4   8991       
8Prod B3001721.0       9113673  
8Prod C220180.0         671449

Now see the impact of transferring products between work centers in batches of 10. What took 4 days, now takes less than 3 days:

Start of Schedule:14/3 04:00 
Transfer batch:  
 
 14/315/316/317/3
Work CenterProductQtyUnits/HourWait Hrs 00:0008:0016:0000:0008:0016:0000:0008:0016:0000:0008:0016:00
6Prod A180130.05210424         
6Prod B300120.0  74969634      
6Prod C220150.0     7712023    
7Prod A180210.54610430         
7Prod B300190.1  68969640      
7Prod C220220.0     7012130    
8Prod A180161.13810438         
8Prod B300170.0  60969648      
8Prod C220180.0     6112138    

If a fast operation follows a slow operation, as in this example, it will stop and start as it waits for each transfer batch to reach it. The 3 pass algorithm avoids this by delaying the start of the fast operation so that it catches up with the slow operation by the time the job finishes. To ensure that the second operation does not finish before the first, it needs to look up the stop, as well as the start of the previous operation. For simplicity these detailed calculations are hidden in this example, but they are explained in the tutorial.

Notice that the Gantt chart now shows the number of units produced in each time bucket. This is done by taking the hours per bucket, as in the previous Gantt chart, and multiplying by a rate per hour.

Sequencing a Multiple Work Center Schedule

These simple examples show each product with the same routing, work center 6 then 7 then 8. Some processes work this way, so sequencing may simply be a matter or sorting operations by due date within work center. Manufacturing processes where the products follow very different routings, may require more sophisticated sequencing rules to be calculated. One such calculation works as follows:

  • the loading on each work center, in hours, is calculated
  • for each job the most heavily loaded work center that it passes through, is identified
  • we consider this to be the job's constraint
  • assuming infinite capacity (for now) we calculate the latest time that the job must start on the constraint, in order to meet its due date
  • we then sort by this date to determine the sequence through each work center

Often it is a good idea to allow the sequences to be overridden manually to see how the schedule responds to changes in sequence.

Putting it All Together

In my experience of several hundred scheduling systems, each one is different, but a typical spreadsheet scheduling system may have the following features:

  • ODBC interfaces with a host ERP or MRP system
  • routings through multiple work centers
  • a BOM with several manufactured components at an assembly operation
  • a separate calendar for each work center
  • a change-over matrix for each work center
  • repetitive production
  • different transfer batch sizes for each product between each work center
  • demand that may explode into several thousand operations
  • a rough pre-schedule to establish a sequence for each operation
  • the push-pull-push 3 pass algorithm
  • Gantt charts with variable sized time buckets

The flow of data through the system would typically be as follows:

Host system Flow of data through the system

Such a system would:

  • have about 20 pages in a workbook
  • be up to 30Mb in size
  • have finite scheduling calculations with up to 150 columns and several thousand rows
  • contain about 10 PivotTables
  • have NO macro code
  • take from 5 to 30 seconds to re-schedule

Author:
Tony Rice
production-scheduling.com

24 Kenilworth Drive,
Kloof 3610, KwaZulu/Natal,
South Africa
Tony Rice graduated with a BA honors Business Degree from Manchester. He worked as a management accountant for the electronics companies, Pye/Philips and Sinclair in the UK. In 1981 he came to South Africa to join Deloitte and Touche Consulting, and later moved to KPMG Consulting as a Director.

Since 1990 Mr. Rice has operated as an independent consultant specializing in production scheduling and supply chain integration. He can be contacted at e-mail address: Production-Scheduling@Mweb.co.za